Northbound Capitol Expressway (between Story Road and S. Capitol Avenue) will be closed with detours in place.
Crews will be installing rebar and pouring concrete onto the superstructure in the median of the intersection. Crews require a full road closure at night to complete this work safely, with minimal impacts to traffic.
WHERE
Northbound Capitol Expressway between Story Road and Capitol Avenue.
WHEN
-
Thursday evening, July 9 through Saturday morning, July 18, and
-
Monday night, July 20 through Friday, July 24.
SCHEDULE
Road Closures: Weekdays: 10 PM – 5:30 AM | Weekends: 10 PM – 9 AM
Work Activities: Weekdays: 8 PM - 5:30 AM | Weekends: 8 PM - 9 AM
WHAT TO EXPECT
-
Noise from crews and heavy construction equipment (back-up alarms)
-
Items colliding and dropping; hammering
-
Traffic delays due to road closures and detours
-
Light needed for visibility
NOTES
Construction activities can change at any time.
Pay attention to changing road conditions and consider alternative routes.
Homes located closest to the construction area may be eligible for overnight hotel accommodation depending on the nighttime activities and predicted noise levels.
Slight arrival delays due to reroutes. Call VTA Customer Service for trip planning support: (408)321-2300
The traveling public may experience traffic delays due to detours, but please remember work is conducted overnight. Overnight work and road closures are necessary to ensure the safety of both work crews and the traveling public.