Crews will be removing falsework from the Superstructure over the median. To do this, crews will be closing 2 lanes along NB Capitol Expressway, between Ocala Avenue and Capitol Avenue.
These lane closures do not occur if a road or intersection closure is taking place.
Crews require space to stage cranes, lifts, and other heavy machinery used to remove the falsework.
None.
Adjacent community members may hear construction noises, including voices, hammering, items dropping/clanging, and backup alarms from heavy equipment. Residents may also see lights necessary to illuminate the worksite.
None.
Travel delays due to lane closures.